The Vita H2O Project Details

Developed by FrontRange H2O, The Vita H2O Project™ leverages over 120 years of combined water infrastructure experience and expert leadership. The project is on track to begin delivering water by 2029.

Colorado landscape sunset

How The Vita H2O Project Works

Discover how The Vita H2O Project operates, from capturing and treating non-tributary groundwater to ensuring top-tier water quality and promoting sustainable water management through reuse. Find details on the aquifer system, treatment processes and northern Colorado water resilience.

Windmill in a Colorado Landscape

Why The Vita H2O Project?

Discover the many benefits of The Vita H2O Project, including affordability, reliability, reusability, water treatment and quality, regional scalability and minimal environmental impact.

Project Timeline

Q2 2025

Landscape in Colorado - Vita H20

First partner agreement complete

Q3 2025

Engineering Design for Vita H2O Project

65% of the engineering design complete along with key components secured early in order to keep the project on schedule

Q2 2026

Construction starting for Vita H20 Project

Construction begins

Q4 2026

Adjudication of water is complete, meaning the water rights tied to the project have gone through water court and are officially recognized.

Q3 2028

Commissioning, including testing, calibrating and verifying The Vita H2O Project™ system before full operations begin

Q1 2029

Delivery of first “wet water,” meaning water is now available and providing treated water to customers